Project:         Phase:    
Prior to beginning construction (in the following order):
  Approval of Construction Plans
  Final Engineer's Estimate (based on as-bid costs), Construction Quantities submitted to City 
  Under and Above Ground bonds with minimum 1-year expiration
  Asphalt Bond with minimum 2-year expiration
  Inspection Fees ($275/day)
  Guaranty Agreement signed
  Final Plat signed and recorded/ original mylar print to Engineering Dept.
  Copy of recorded restrictive covenants to Engineering Dept.
  Notification of Start Date
Release of Underground Bond (#___________)
  Receipt of Plan Approval Notification from OEPA
  Sanitary and Water completed and tested per approved plans
  Storm sewer completed and tested per approved plans
  Necessary Utility Easements recorded/copies to Engineering
  Water
  Sanitary
  Storm
  Necessary Access Agreements recorded/copies to Engineering
  Sanitary and Storm Sewer Lateral staking complete
Release of Above Ground Bond (#___________)
  Curbs, Underdrains, Subgrade, Stone base, Base course asphalt per approved plans
  Subdivison Boundary Monumentation installed 
  Curb Ramps installed per approved plans
  Other walk installed as required (back lot, etc.)
  Final Grade of Rights-of-Way
  Seed and Mulch
  Submittal to Traffic Commission for subdivision signage
Release of Asphalt Bond (#___________)
  Final Asphalt Course
  Pavement Monumentation
  Curbing, curb ramps, sidewalks remain in acceptable condition