| Project: | Phase: | ||||||||
| Prior to beginning construction (in the following order): | |||||||||
| Approval of Construction Plans | |||||||||
| Final Engineer's Estimate (based on as-bid costs), Construction Quantities submitted to City | |||||||||
| Under and Above Ground bonds with minimum 1-year expiration | |||||||||
| Asphalt Bond with minimum 2-year expiration | |||||||||
| Inspection Fees ($275/day) | |||||||||
| Guaranty Agreement signed | |||||||||
| Final Plat signed and recorded/ original mylar print to Engineering Dept. | |||||||||
| Copy of recorded restrictive covenants to Engineering Dept. | |||||||||
| Notification of Start Date | |||||||||
| Release of Underground Bond (#___________) | |||||||||
| Receipt of Plan Approval Notification from OEPA | |||||||||
| Sanitary and Water completed and tested per approved plans | |||||||||
| Storm sewer completed and tested per approved plans | |||||||||
| Necessary Utility Easements recorded/copies to Engineering | |||||||||
| Water | |||||||||
| Sanitary | |||||||||
| Storm | |||||||||
| Necessary Access Agreements recorded/copies to Engineering | |||||||||
| Sanitary and Storm Sewer Lateral staking complete | |||||||||
| Release of Above Ground Bond (#___________) | |||||||||
| Curbs, Underdrains, Subgrade, Stone base, Base course asphalt per approved plans | |||||||||
| Subdivison Boundary Monumentation installed | |||||||||
| Curb Ramps installed per approved plans | |||||||||
| Other walk installed as required (back lot, etc.) | |||||||||
| Final Grade of Rights-of-Way | |||||||||
| Seed and Mulch | |||||||||
| Submittal to Traffic Commission for subdivision signage | |||||||||
| Release of Asphalt Bond (#___________) | |||||||||
| Final Asphalt Course | |||||||||
| Pavement Monumentation | |||||||||
| Curbing, curb ramps, sidewalks remain in acceptable condition | |||||||||