Construction Cost Inspection Fee
($275/day - 1 day minimum)
Underground  (1 yr. minimum)
Sanitary Sewer  (# total footage) $     days $  
Storm Sewer   (# total footage) $     days $  
Waterline   (# total footage) $     days $  
Rough Grading & Detention Ponds $   (include with storm sewer)
TOTAL UNDERGROUND $     days $  
Above Ground  (1 yr. minimum)
Curb & Gutter, Underdrain,
Subgrade, Agg Base, Asphalt Base
(# centerline footage) $     days $  
Curb Ramps/Walks, Finish Grade,
Seed & Mulch $   (include with curb & gutter)
TOTAL ABOVE GROUND $     days $  
Asphalt  (2 yr. minimum) 
Asphalt Surface Course (# centerline footage)
TOTAL ASPHALT $     days $  
GRAND TOTAL INSPECTION FEE $  
Up Arrow Callout: Costs for bonding purposes shall be based on actual as-bid amounts.  A statement shall be included indicating the source of the estimates.
Up Arrow Callout: Suggested method of calculating inspection days:

Sanitary - 5 days/1000 LF x .75
Storm - 3 days/1000 LF x .75
Waterline - 2 days/1000 LF x .75
Above Ground - 4 days/1000 LF x .75
Asphalt - 1 day/1000 LF x .75
Construction costs are based on
actual bid amount.
 
P.E. Signature
Three bonds and inspection fees are required for each subdivision, to be filed simultaneously prior to beginning 
construction.  Bonds will be released upon acceptance of the improvements by the Chief Engineer.