Construction Project Update for July 12-19, 2019

Post Date:07/11/2019 4:00 PM
The City of Findlay is performing numerous construction projects throughout the city, weather and contractor schedule permitting for the status of some of the projects. Listed below are some of the projects and the restrictions that result from the ongoing projects. These restrictions are in effect from July 12-19, 2019.

WOODWORTH DR. - Fostoria Ave. to Cul-De-Sac. - Will be closed to through traffic on Friday, July 12, 2019, and Saturday, July 13, 2019, for asphalt resurfacing.

S. BLANCHARD STREET – Sandusky St. to South St. – The two northbound lanes of S. Blanchard Street will be closed to all traffic. During the closure the southbound lanes of S. Blanchard Street will serve as the travel lanes for both northbound and southbound traffic. Southbound traffic on S. Blanchard St. will also be prohibited to turn eastbound onto E. Sandusky Street. Residents and business within the area will still have access to their respective drives, but will experience some delays when crews are working in front of the property.

S. BLANCHARD STREET & LINCOLN STREET INTERSECTION – The intersection of Blanchard St. and Lincoln St will be closed to all traffic at all times for waterline installation starting on July 8, 2019, and lasting until July 26, 2019. A detour will be set up to help direct traffic around the closure.

SIXTH STREET- Eastview Dr. to Burson Dr. - Will be reduced to one lane between the two blocks. A temporary traffic light will be set up to direct traffic through the construction zone.

Avoid these blocks if possible. Short delays are expected in these areas over the next week.

The Engineering Department will release updates on information and schedules when it becomes available. Please do not hesitate to contact us if you have any questions about any of these projects at 419-424-7121.